2.0 MW Interior UPS skid
Location(s)
Numerous Locations
Dimensions
8.5’ x 22’
Power
2.0 MW
Highlights
40+ units deployed / RAF and Overhead ProductTactics Employed
Project focus related to footprint and logistics for moving into deeper interior spaces. The design allowed for 80% of the work to be performed outside of the critical path of receiving equipment. This project represented a step into buy vs. build, which takes traditional trade work and shifts it to another subcontractor’s scope of work.
Lessons Learned
Incorporate everything possible into the factory rather than the field. These products have several vendor-installed components that are done at startup, but can easily be installed and tested prior to shipping. This helps avoid issues with parts getting lost offsite, and saves time if anything goes wrong.